Suppliers and Specs

Submittals and RFIs Explained for Equipment Suppliers

Two documents move most of the paperwork on a construction job. Here is how each works and how to keep them from slowing a project down.

Key takeaways

  • A submittal proves that the product you plan to supply meets the specification. An RFI asks the design team a question the documents do not answer.
  • Most rejected submittals fail on completeness, not on the product itself.
  • Fast, specific, well-organized responses protect both your schedule and the contractor's.

On a construction project, equipment suppliers rarely deal with the owner directly. They work through the contractor and the design team, and the paperwork that connects them is mostly two things: submittals and requests for information, or RFIs. Knowing how each one works makes a supplier easier to work with and keeps orders moving.

What a submittal is

A submittal is a package of documents showing that a product, as the contractor intends to buy it, meets the project specification. The engineer of record reviews it and returns it with a status. Common statuses are approved, approved as noted, revise and resubmit, and rejected. Exact wording varies by project.

Typical submittal contents include:

  • Product data sheets with the exact model or series marked, not a whole catalog page.
  • Dimensional drawings and connection details.
  • Materials of construction and the standards they meet.
  • Pressure, temperature and performance ratings.
  • Test reports or certifications the specification calls for.
  • Installation, operation and maintenance information.
  • A line by line comparison against the specification section, noting any deviations.

What an RFI is

An RFI is a written question sent through the contractor to the design team. It is used when drawings conflict, a specification is unclear, a substitution is being proposed, or a field condition does not match the documents. The answer becomes part of the project record.

Steps for a clean submittal

  1. Read the specification section and the related general requirements before assembling anything.
  2. Check the required submittal format, number of copies and naming rules.
  3. Mark every product, size and option that applies to this project.
  4. Answer each specification requirement directly. Flag any difference openly rather than hoping it goes unnoticed.
  5. Send it to the contractor early enough to allow for a review cycle, and for a second one if needed.
  6. Track the status and respond to comments quickly.

Writing a useful RFI

A good RFI is short and specific. It names the drawing sheet or specification section, states the conflict or gap, and proposes an answer when possible. Compare these two: "Please clarify the valve requirements" is vague. "Section references one standard in paragraph 2.1 and a different one in paragraph 2.4. Please confirm which governs" can be answered in one reply.

Common reasons submittals come back

  • Missing or unmarked model information.
  • Ratings that do not match the schedule on the drawings.
  • Unlisted deviations from the specification.
  • Outdated documents or the wrong revision.
  • Required certifications left out.

Why timing matters

Equipment cannot be released for manufacturing until the submittal is approved, and long lead items have little room to absorb delays. A week lost in review can become a week lost on delivery. Suppliers who ask about review durations at the start, and who keep a log of open items, tend to become the ones contractors call again.

The simple rule is to make the reviewer's job easy. A complete, well-marked package with honest notes on deviations usually moves through review faster than a thick one with gaps.

Found this useful? Pass it on.